移至主內容

Dazhu Village – the last permanent-housing village

2012/07/09 18:20
2,361次瀏覽 ・ 1次分享 ・ 0則留言
PeoPo推 1
檢舉

In the carnage of Typhoon Morakot, only two households in Dazhu Village received damage. However, last January’s assessment by the Soil and Water Conservation Bureau declared that with the continuing danger of landslides around streams behind the village, the area was no longer fit for human habitation, setting the wheels of village relocation in motion. The relocation process, however, has been anything but smooth. The nearby village of Fushan moved to a new permanent housing settlement last July, but Dazhu residents may have to wait until July of this year before their new homes are ready. A lack of communication between government officials and residents during this waiting period has given rise to anxiety and doubt. Currently, all but 10% of permanent housing developments constructed after the Morakot disaster have been completed, New Dazhu Village being included in this. Located to the north of Jumaqup Village and covering 2.4 hectares, New Dazhu Village has cost NTD80 million, is around 5-6 kilometers and a 15-minute drive away from the original village. The village, which will house 30 families, is currently rushing to finish construction. However, the opinions of villagers on relocation are split, and from a total of 77 households, 10 families have insisted on remaining on their original land. The Dazhu Village relocation situation is the epitome of the post-Morakot rebuilding process. Not only has there been a lack of consensus amongst the villagers, but the government also spent around a year searching for suitable land after which it was unable to agree on a price with the landlord, finally paying the expropriated land price.

Once building work was ready to commence the plans failed to get the approval of public welfare bodies and it wasn’t until World Vision Taiwan stepped in did things begin to move forward. A series of problematic situations meant that construction work on new Dazhu Village did not get underway until February of this year. Originally scheduled to be completed by the end of June, after the recent spate of heavy rain affected construction, a spokesperson from Morakot Post-Disaster Reconstruction Council said the earliest the village would be finished was mid-July. As the last permanent-housing village to be completed, perhaps New Dazhu Village can draw on the community-building experience of other tribes, helping to smooth out the road ahead.

PeoPo 公民新聞

Dazhu Village – the last permanent-housing village
URL: http://www.peopo.org/news/97691

 

(以下是中文對照)

照片

大竹本部落-最後一批完工的永久屋基地 ( 政在發聲)

台東縣大竹本部落八八風災時,大竹本部落只有兩戶受到土石流損害,但經農委會水土保持局評估,後方野溪仍有土石流的危險,因此早在前年1月就已劃定為特定區域,確定該部落不再適合人居,全村必須遷村。但是遷村過程漫長而波折,隔鄰的富山部落早在前年7月就已搬進永久屋,大竹永久屋卻可能要到今年7月才能完工,等待期間由於官民溝通不足,族人間又產生許多不安和質疑。目前,所有八八水災永久屋興建工程大約還有一成沒有完工,大竹永久屋基地即是其中之一。大竹本部落永久屋斥資八千多萬元,選定於更北邊的愛國埔段,距本部落約五、六公里遠,車程15分鐘,共有30戶,佔地約2.4公頃,目前工人正在趕工。族人對於遷村意見不一,全部落共77戶,至今仍有十多戶人家堅持留在原居地。大竹本部落遷村過程是八八水災重建工程延宕的部分縮影。除了居民沒有共識外,政府光是找地就花了一年多,又與地主談不攏徵收價碼,等到可以興工時,又缺乏公益團體援建,直到去年4月才由台灣世界展望會進場協助,一連串的狀況讓大竹永久屋直到今年2月才開工,本來預定6月底完工,然而連日來的大雨打亂進度,重建會家園重建處表示,最快可能得等到7月中才能完工。不過作為最後一個興建完成的永久屋基地,大竹本部落或許能吸取其他部落的社區營造經驗,在災後重建的路上走得更順遂。

 

為擴大服務範圍,自2010年4月起,PeoPo每周精選三則公民報導及相關活動與發展,翻譯成英文摘要,讓更多關心台灣公民新聞的朋友,瞭解台灣在地大小事。

發言應遵守發言規則

回應文章建議規則:

  • 文章屬於開放討論空間,回應文章的議題與內容不代表本站的立場
  • 於明知不實或過度謾罵之言論,本站及文章撰寫者保留刪除權
  • 請勿留下身份證字號、住址等個人隱私資料,以免遭人盜用,本站不負管理之責
  • 回應禁止使用HTML語法

公民記者留言請先登入

公民記者留言請先登入